North Perth

Project number Project 35
Detailed design 2028 (to be confirmed)
Estimated construction start date Mid 2030
Estimated duration Approximately 12 months

  Transformer

Primary equipment site with a transformer.

  Combination

Primary equipment site with a combination of equipment.

Overhead transmission lines

High voltage transmission power lines. These lines will not be undergrounded.

Project area boundary

There are eight project areas as marked by the pink boundary lines.

Was this page helpful?