North Perth / Mount Lawley

Project number Project 347
Detailed design In progress
Estimated construction start date Early 2025
Estimated duration Approximately 16 months

Western Power and the City of Vincent are working together to convert the overhead electricity distribution network in North Perth / Mount Lawley area to underground power. As part of this project, Western Power will be installing new underground cabling, primary equipment (transformers and switchgear) and LED streetlights.

PRIMARY EQUIPMENT INSTALLATION

Primary equipment units are an essential component in the delivery of underground power. 

They are electrical infrastructure, such as ground mounted transformers and switchgear units that enable the distribution of electricity to residents through the underground network.

Where possible, this equipment will be located in parks, public open spaces, road reserves and verges. Every effort has been made to ensure the chosen site locations have the lowest impact on the surrounding area, with landscaping or screening added where possible and the total footprint of the primary equipment kept to a minimum. 

The initial round of community engagement on the primary equipment sites for this project area closed on Monday 28 August 2023. In response to community feedback, adjustments have been proposed for some equipment locations as follows:

  • An additional equipment site is now proposed for the verge on the corner of Grosvenor Road and Fitzgerald Street, North Perth.
  • The number of proposed equipment items to be reduced in Leake Street Reserve (corner of Leake Street and Alma Road, North Perth).
  • An existing equipment location in Hyde Park (near the corner of Throssel and Glendower streets) will not be increased in size.

The new proposed site would reduce the impact on the other two sites where the number of items of equipment initially proposed were considered excessive by the local community. Further consultation letters have been sent to property owners near the proposed new site.

A second round of consultation closed on 31 October 2023.

Feedback received on these proposals is currently being reviewed by the City and by Western Power, and the network design will be finalised once the matters raised by the community in relation to these sites have been addressed.

  Transformer

Primary equipment site with a transformer.

  Combination

Primary equipment site with a combination of equipment.

FAQs

What is Primary Equipment?

Primary equipment units are an essential component in the delivery of underground power. 

They are electrical infrastructure, such as ground mounted transformers and switchgear units that enable the distribution of electricity to residents through the underground network.

This equipment was previously located on overhead poles, and as part of the conversion to underground power it is being moved to locations on the ground, generally in parks and on public verges.

Primary equipment is housed in green metal cabinets. Depending on the site and installation requirements, a retaining wall may also be required. 

Each site will have its own unique installation requirements to comply with Western Power’s technical specifications, Australian Standards and for community safety.

Western Power endeavours to minimise the footprint of each primary equipment site and has worked closely with City of Vincent to determine each site location following extensive analysis of the network, technical standards and financial costing, and taking into consideration public safety, heritage, environmental and social impacts. 

When will primary equipment be installed for the North Perth/Mount Lawley underground power project?

Primary equipment will be installed as part of the construction of underground power. Work will start in 2024/2025 and is expected to take approximately 16 months to complete.

What are the construction impacts of primary equipment sites?

During the primary equipment installation works, there may be some construction impacts such as dust, vibrations and noise.

Noise impacts will be minimised by using equipment that is well maintained and fit for purpose, as well as by scheduling times to have the least impact on residents.

Contractors generally work within regular construction hours. If after hours work is required for public safety reasons or to minimise the outage impact to residents, the contractor will work with the City of Vincent and other relevant authorities to schedule the most appropriate time. Impacted residents will be informed prior to these out of hours works commencing.

To complete the work safely, traffic management may be in place. Please take care around work sites and follow the appropriate signage.

What is involved in the construction of primary equipment sites?

Each primary equipment site is installed according to Western Power’s technical specifications which meet or exceed the Australian Standards to ensure community safety and efficient operation of the equipment.

Although primary equipment sites are not all the same, the steps involved in construction are: 

  • Construction starts with the site being pegged with survey stakes to show the actual footprint.
  • The ground is checked for third party services before being excavated.
  • Once the hole has been dug, the soil at the base is levelled and compacted to prepare for a crane to position the equipment. 
  • The equipment is installed correctly, then the electrical cables are terminated and tested.
  • When this is complete the site will be backfilled and compacted.
  • The site will have a border installed, or if required a retaining wall, then a layer of blue metal placed around the assets.

Does the primary equipment make any noise once installed?

Primary equipment does emit a slight humming sound as part of normal operation. The noise can be compared to that made by a quietly running fridge.

The locations of primary equipment are selected to comply with the Western Australian Environmental Protection (Noise Regulations) 1997

Hyde Park

Is Western Power complying with the relevant Heritage Act/s for equipment sites in heritage areas?

Western Power undertakes an initial Heritage Assessment of each underground power project area before starting network design. Hyde Park, as a registered Aboriginal Cultural Heritage site, is the only affected site in the North Perth/Mount Lawley project area.

Once the network design for this project area is completed, Western Power will undertake a further Due Diligence Assessment as required by the Aboriginal Cultural Heritage Act 2021.  They must follow the correct processes to obtain relevant authorisation/s prior to placing equipment within Hyde Park.

 

Why can't the equipment planned for Hyde Park be located elsewhere?

There is one new primary equipment site proposed within Hyde Park to serve the North Perth/Mount Lawley project area.

Primary equipment needs to be located within a few hundred metres of those properties being supplied with power. In this instance, the only viable alternatives would be verges next to or in front of someone’s home or business, or on private property. Vincent aims to reduce impacts on people’s homes and businesses by identifying City-owned land such as parks and car parks, wherever possible.

More information and feedback

The current round of community consultation closed on Tuesday, 31 October 2023. Western Power will finalise the underground network design once the feedback has been reviewed.

If you have any questions about the location of this primary equipment, please contact us via 9273 6000 or mail@vincent.wa.gov.au.

For more information about this project, sign up to Vincent’s eNewsletter.

BACK

Was this page helpful?